RN No. 215
Project Name HAGL Phase-2
Developer HAGL Myanmar Co.,Ltd.
Status on-going
Basement
Storey 2B + (3Nos. of 33 Storey + 2Nos. of 23 Storey Offi
Building Height
Location No.192, Corner of Kabaraye Pagoda Road & Industrial Road.
Region
State
Project Status
Architecture 1. Presented Architectural presentation.(29.5.2017) 2. Submit Final Architectural drawing (4) sets for Residential Buildings. (31.10.18) 3. Discussion with foreign Architect and National Counterpart about Residential Buildings. (1.11.2018) 4. Principle Recommended on Architecture, Deep Excavation, Foundation & Structure for Residential Buildings. (19.11.2018)
Structure 1. Recommended for PLT (2.6.2017) 2. Discussion for PLT report. (29.1.2018) 3. Recommended piling. (29.11.2017) 4. Waiting presentation for all design. 5. Comment for overall (6.11.2018) 6. Comment reply for overall from company.(15.11.2018) 7. Principle Recommended on Architecture, Deep Excavation, Foundation & Structure for Residential Buildings. (19.11.2018)
Electrical 1. Presentation(25.3.2019). 2. Comment sent on (1.4.2019). 3. Company submit reasons for the delay (3.5.2019). 4. Company submit reasons for the delay (10.6.2019). 5. Waiting for comment reply.
ACMV 1. Presentation(25.3.2019). 2. Comment sent on (1.4.2019). 3. Company submit reasons for the delay (3.5.2019). 4. Company submit reasons for the delay (10.6.2019). 5. Waiting for comment reply.
Water and Sanitation 1. Presentation(25.3.2019). 2. Comment sent on (1.4.2019). 3. Company submit reasons for the delay(3.5.2019). 4. Company submit reasons for the delay(10.6.2019). 5. Waiting for comment reply.