RN No. | 219 |
Project Name | Emerald Bay Project |
Developer | Yangon Golden Paragon Investment Co.,Ltd. |
Status | under-construction |
Basement | - |
Storey | Phase. I [ 2nos. of 32 Storey Residential Building |
Building Height | - |
Location | Shue Khin Thar Circle Twp Road, Tharkayta Township. |
Region | |
State |
Project Status | |
Architecture | 1. Submit Architectural drawing (1) set with HIC approval. 2. Presented Phase (I) Conceptual Architectural presentation. (18.3.19) 3. Not submit Final Architectural Drawing and documents |
Structure | 1. Recommended for ULT (2nos) from CQHP. (17.9.2018) 2. PLT (method-3) from Company (15.3.2019) 3. Recommended for Piling (method-3) by CQHP (19.3.2019). 4. Recommeded for WLT (9nos) from CQHP (14.5.2019). 5. Third comment from CQHP (20.6.2019). 6. Waiting for comment reply. |
Electrical | 1. Submitted drawing on (7.5.19) 2. Presentation on (13.5.19) 3. Sent the comment on (20.5.19) 4. Submitted drawing on (13.6.19)(1)Set. 5. Discuss with the National Designer(20.6.19) |
ACMV | 1. Submitted drawing on (7.5.19) 2. Presentation on (13.5.19) 3. Sent the comment on (20.5.19) 4. Submitted drawing on (13.6.19)(1)Set. 5. Discuss with the National Designer (20.6.19) |
Water and Sanitation | 1. Presentation on (13.5.19). 2. Submit letter that company will obey CQHP’suggestions on (17.5.19). 3. Comment and Recommended in principle.(20.5.19) 4.Submit Revised (1) set on (13.6.19). 5.Checking on revised design. |