Back to Project Lists
RN No. | 138 |
Project Name | Shwe Gone Emotion Tower |
Developer | December Construction Co.,Ltd |
Status | on-going |
Basement | - |
Storey | 4B+32 |
Building Height | - |
Location | No.297-293, Corner of Bogyoke Aung San & Pan Soe Dan Road, Kyauktada Township, Yangon. |
Region | |
State |
Project Status | |
Architecture | 1. Submitted Conceptual Architectural Drawing for Pile Load Test Presentation.(Without Designer Sign) |
Structure | 1. Pile Load Test recommended. (6.3.14) 2. Remind to submit PLT report. (11.8.14) 3. Remind to submit Design Document and PLT report. (22.1.15) 4. Remind to submit PLT new method statement for PLT. (6.4.15) 5. D.Wall recommended. (18.5.15) 6. Remind to submit Design document and WPLT. (14.8.15) 7. Remind to submit Design document and WPLT. (8.10.15) 8. Remind to submit Design document and WPLT. (9.4.18) 9. Waiting for company's reply. |
Electrical | 1. Not yet submitted by Developer. |
ACMV | 1. Not yet submitted by Developer. |
Water and Sanitation | 1. Not yet submitted by Developer. |